How we repair a loading bay – hot works, done safely
A weld repair on a dock leveller's rear angle, start to finish: hot works permit, bay monitoring, lock-off, firewatch and sign-off – all in BayHQ.
First: the site office - and a hot works permit
We tell the office what we're doing, and site issues a hot works permit.
What a safe hot works repair looks like
Welding on a loading bay is hot works. Done properly, it starts long before anyone strikes an arc – and it carries on after the welding stops.
Permit and RAMS first
We go to the site office and tell them exactly what we're doing. Site issues a hot works permit, and both engineers sign the RAMS in BayHQ. The permit is photographed into the job and the firewatch time on it is set in BayHQ, so it's on record before work starts.
Out of use – and everyone can see it
On a bay with our bay monitoring, the engineer takes the bay out of use on their phone once the office has agreed. The outside traffic light goes red, and the office PC, the drivers' TV and the warehouse TV all show the bay is out of use – nobody gets sent to it. Only an engineer can put it back in use. We still put our van on the bay and the barriers out, raise the deck onto its maintenance strut, and isolate, lock off and tag the panel. Bay monitoring doesn't replace lock-off – it adds to it.
Fire precautions
Anything that can burn – pallets, cardboard, shrink-wrap – is moved well away. A fire blanket goes in the pit and an extinguisher at the work. Welding screens stop arc flash reaching anyone in the warehouse, and the welder wears a helmet with the right filter, leathers, gauntlets and boots. The second engineer is the firewatch the whole time.
The firewatch – timed in BayHQ
When the welding stops, the firewatch timer starts in BayHQ for the time on the permit. The firewatch stays at the bay checking the pit, under the deck and behind the screens, and every check is logged until the time is up.
Signed off – and back in use
After a full test, site signs the repair and the hot works permit off on the engineer's phone, and the record goes straight to you. Then the engineer puts the bay back in use: the light goes green and every screen shows it's ready.